The Project in Numbers
Key indicators
21,140 m²
storage space
970 square meters
office space
Hultafors
BTS project client
AutoStore
faster and more accurate service
FM Global 8-34
fire safety standard
Solar + EV charging
infrastructure supporting modern operations
Challenges
What challenges did we face in this project?
The integration of production and logistics
The facility had to simultaneously support production processes, internal logistics, and a high degree of operational repeatability.
High technical and safety requirements
The project required compliance with strict fire safety standards and technical quality assurance appropriate for manufacturing operations.
Readiness for automation and growth
The project was intended to support day-to-day operations while also leaving room for further process optimization and scaling.
7R Solutions
How we carried out the project
AutoStore for greater efficiency
The implementation of the AutoStore system has streamlined warehouse operations, increased service speed, and improved process accuracy.
Safety in accordance with FM Global 8-34
The facility was designed in accordance with stringent fire safety standards, which enhances operational safety and reduces risk.
Infrastructure supporting modern operations
We have installed a PV system, EV charging stations, and super flat floors, which support the smooth operation of automation systems and the flexible expansion of operations.
Scope of work
Project Objectives
Support for precise and repeatable operations
The facility's readiness for automation and expansion
A combination of safety, quality, and operational efficiency
Scope of work
Scope of Work 7R
Implementation of a build-to-suit project for manufacturing and logistics
Preparing the facility for AutoStore implementation
Implementation of technical and infrastructure solutions to support development
Schedule
Implementation Schedule
1
Design of a facility for manufacturing and logistics
designing an environment that supports precision operations, safety, and future automation
2
Implementation of technical solutions
Construction of the facility, including AutoStore, super-flat floors, and infrastructure supporting modern operations
3
Preparing for surgery
launching a facility ready to efficiently support production and warehousing processes
Results
Measurable project outcomes
21,140 m²
storage space
970 square meters
office space
AutoStore-ready operations
faster and more accurate service supported by automation and the facility's technical specifications
Gallery
Photographic documentation