The Project in Numbers
Key indicators
58,700 m² GLA
Modern logistics space
FIEGE / Zalando
tenant of the property
Łozienica
7R Park Szczecin Goleniów II
FM Global-compliant
fire safety guidelines
PV-ready
solutions that support efficient operation
Returns logistics
a facility designed to handle returns
Challenges
What challenges did we face in this project?
Short turnaround time
The client needed a solution that could be implemented quickly, without compromising on quality, security, or operational readiness.
Technical and Safety Requirements
The facility had to meet advanced fire safety requirements and technical standards appropriate for large-scale operations.
Integration of intralogistics processes
The key was the smooth implementation of the picking infrastructure and ensuring readiness to handle complex e-commerce and returns processes.
7R Solutions
How we carried out the project
A BTS facility tailored to the client's operations
We designed and delivered a warehouse tailored to the specific operational needs of FIEGE and Zalando, taking into account the scale of their operations and the unique challenges of returns logistics.
Technical Solutions and Safety
The project was designed using state-of-the-art technical systems and a rigorous approach to fire safety in accordance with FM Global’s stringent standards.
Support for intralogistics implementation
7R coordinated the intralogistics-related work and assisted in obtaining the necessary permits for the picking tower, enabling the facility to achieve operational readiness without delay.
Scope of work
Project Objectives
Quick start-up of operations
Full alignment of the facility with e-commerce logistics and returns
High standards of safety and technical quality
Scope of work
Scope of Work 7R
Build-to-suit project implementation
Coordination of the implementation of intralogistics infrastructure
Formal and technical support for the launch of the picking tower
Schedule
Implementation Schedule
1
Design and Operational Alignment
Design of a BTS facility for e-commerce logistics, returns processing, and security requirements
2
Construction of the facility and technical infrastructure
implementation of technical solutions, preparation of the facility for high-intensity processes
3
Acceptance and Commissioning
coordination of arrangements, support for the implementation of intralogistics, and achievement of operational readiness
Results
Measurable project outcomes
58,700 m²
a modern BTS logistics facility
Ready for returns logistics
a facility designed to handle large-scale returns
Operational readiness
readiness to launch advanced e-commerce operations and a picking infrastructure