The project by the numbers
Key indicators
140,000 m² GLA
Warehouse space
14 months
Lead time
2,500 jobs
Positions created
6 MW PV
The Power of Photovoltaics
120 docks
Charging stations
100% automation
Full automation
Challenges
The challenges we faced in this project
Scope of the project
Construction of a comprehensive 140,000-square-meter facility in a short time
Technical specifications
Stringent requirements for automation
Environmental goals
Ambitious BREEAM Excellent goals
7R Solutions
How we implemented the project
Process
Close coordination of contractors'
: Just-in-time scheduling
Technology
Full automation of the sorting plant's WMS systems
ESG
6 MW photovoltaic EV charging stations
Scope of work
Project assumptions
Large-scale BTS facility
Full automation
Scope of work
Scope of Work 7R
Design and construction
BREEAM certification
ESG infrastructure
Schedule
Implementation schedule
1
3-month project
Design and permits
2
Construction: 10 months
Construction implementation
3
1-month transfer
Tests and acceptance
Effects
Measurable project outcomes
3-month project
Ahead of schedule
Construction: 10 months
The largest BTS facility
1-month transfer
High certification